partial substitution of project number for WBS element

$
0
0

Hello Vadiraj ,

 

Indeed the purpose is that I use a standard template to create projects with copy.

 

My Standard Template is existing of

 

P.1111-1111 ( Level 1)

P.1111-1111.01 ( Level 2)

P.1111-1111.02  ( Level 2)

P.1111-1111.03  ( Level 2)

P.1111-1111.04  ( Level 2)

 

When I create a project by copy ( for example P.1000-0001 project definition), the substitution would change the WBS's also in P.1000-0001 but only P.1111 is changed in P.1000. -1111 stays and will not be changed in -0001.

 

What do you mean with lower level WBSE structure is it truncated ?

 

Thank you

 

Davy