Hi Ramayya
Net requirements calculation done by MRP is very simple:
Requirements - Receipts = Replenishment proposal
You have a requirement of 100 and only 90 as receipt, therefore, MRP will generate a new planned order of 10. Therefore, you have to manually adjust the PIR quantity.
BR
Caetano