Yes, in OPJJ you can set the "Include planned orders" at either:
blank = do not include any planned orders
X = include all planned orders
A = check firm planned orders only; think of these as capacity leveled in CM25
B = check planned orders that are completely confirmed; think of these as capacity leveled in CM25 AND they have all of their component materials (you've done an ATP check on the planned order using MDVP and the planned order is not missing any component materials)
So option B is the safest; you have not only the capacity but also the component materials to make the planned order
Option A is a possibility too but you are guaranteeing only that you have the capacity.
Hope this helps.